Electrical Takeoff: How to Do It Step by Step (With a Worked Example)
An electrical takeoff is a quantity count of everything on the electrical drawings: devices (receptacles, switches, boxes) and lighting fixtures by count, branch and feeder conduit by linear foot and size, wire derived from conduit length × number of conductors + makeup, and gear (panels, switchboards, transformers, disconnects) by each. Work from the symbol legend and schedules, count by type and by area, add vertical drops and waste, then apply labor units to each item. The steps and worked example below walk through it.
Electrical is one of the most item-heavy takeoffs in construction. A modest office tenant buildout can have hundreds of devices, a dozen fixture types, and thousands of feet of conduit and wire — and every one of those items carries its own labor. Miss a fixture type or forget the drops from ceiling to device height and the bid is light before you price a single hour.
This guide covers how to do an electrical takeoff step by step, with a worked example, so you understand every quantity before you trust a tool to calculate it.
What an electrical takeoff includes
A complete electrical takeoff breaks the job into systems, each measured in the unit that matches how it’s installed and priced:
| System | Take off by | Typical items |
|---|---|---|
| Branch devices | Count (EA) | Duplex, GFCI, quad and dedicated receptacles; switches, dimmers, occupancy sensors; junction boxes |
| Lighting | Count by fixture type | Troffers, downlights, wall packs, exit/emergency, plus whips and supports |
| Branch wiring | Linear feet (LF) | EMT or MC cable, home runs, the conductors inside |
| Feeders | LF by size | Feeder conduit and conductors from the one-line diagram |
| Gear | Each | Panelboards, switchboards, transformers, disconnects, meters |
| Equipment connections | Each | RTUs, condensers, water heaters, kitchen equipment, motors |
| Low voltage / fire alarm | Count + LF | Data, devices, pathways (if in your scope) |
| Site | Count + LF | Pole lights, bases, underground conduit, trenching |
1. Read the right sheets first
Before you count anything, spend 15 minutes with the sheets that tell you what you’re counting:
- Symbol legend and general notes (usually E-001 or E0.0). Every symbol you’ll count is defined here, along with wiring methods — whether MC cable is allowed or everything is EMT changes your whole branch takeoff.
- Lighting fixture schedule. Fixture types (A, B, C…), mounting, wattage, and any emergency battery packs.
- One-line / riser diagram. Service size, gear, and every feeder with its conduit and wire size.
- Panel schedules. Circuit counts per panel — your sanity check at the end.
- Mechanical and plumbing sheets. Equipment that needs a power connection and disconnect often only shows up here.
- Division 26 specs and addenda. Device grade, color, box requirements, and scope changes.
2. Count devices
Count every device symbol on the power and lighting plans by type. Keep separate line items for each device because each one has a different material assembly and labor unit:
- Duplex receptacles (standard, GFCI, weather-resistant, USB, dedicated)
- Quad / double-duplex receptacles and floor boxes
- Single-pole, 3-way and 4-way switches; dimmers; occupancy/vacancy sensors
- Junction boxes and equipment connections shown on the plan
Count by floor or area rather than the whole building at once. It’s easier to check, it matches how the job will be built and billed, and it makes your Schedule of Values easy to produce. Mark each symbol as you count it — in software, that’s automatic; on paper, use a highlighter per type.
Device assembly: one “duplex receptacle” in your estimate is really a box, a mud/plaster ring, the device, a cover plate, connectors, and the labor to install all of it. Build that assembly once and every count prices itself.
3. Count lighting fixtures
Count fixtures by the type tag from the fixture schedule, not by how they look on the plan — two identical-looking symbols can be different fixtures. For each type, also carry:
- Whips (typically one per lay-in fixture)
- Supports (independent support wires, seismic clips where required)
- Emergency battery packs or generator-fed fixtures
- Controls — sensors, dimming, and low-voltage control wiring
Exit signs and emergency units are frequently on a separate symbol or note — don’t let them hide.
4. Measure branch conduit and convert to wire
Branch wiring is where most electrical takeoffs go wrong, because the plans usually show circuits with tick marks and home-run arrows rather than every foot of pipe. There are two ways to handle it:
- Measure the runs. Trace conduit from device to device and the home run back to the panel, adding a vertical drop from the ceiling to each device (ceiling height minus device mounting height) and a rise at the panel.
- Use an average per device. Many estimators carry an average LF of branch conduit per device based on historical jobs of the same type, then measure home runs separately. Faster, but only as good as your history.
Once you have conduit length, wire is a formula, not a second takeoff:
Wire from conduit:
Wire LF = conduit LF × number of conductors × (1 + makeup %)
A 3/4″ EMT run with a hot, neutral and ground (#12 THHN) = 3 conductors. Makeup covers the extra length at boxes and terminations; many estimators use 5–10% and adjust from their own job history.
Add conduit fittings (couplings, connectors, straps) per 10 or 100 feet based on your standards, and a waste factor on the conduit itself.
5. Take off feeders
Feeders come from the one-line diagram and feeder schedule. For each feeder:
- Measure the route length on plan from source to load, plus vertical rises between floors and drops into gear.
- Record conduit size and conductor size and count (phases, neutral, ground).
- Add makeup at each end for terminations — on large feeders, a fixed length per end is more accurate than a percentage.
Large copper feeders are often the single most expensive material line in the estimate, so get the routing right instead of drawing a straight line between panels.
6. Gear and equipment connections
Take off panelboards, switchboards, transformers, disconnects, and meter sockets as individual items from the one-line and panel schedules. Many contractors carry quoted gear as a lump sum with its own install hours rather than running it through the normal per-unit pricing.
Then go through the mechanical, plumbing and food-service sheets for equipment connections: rooftop units, condensers, exhaust fans, water heaters, pumps, and kitchen equipment. Each typically needs a disconnect, a short conduit run, flex/whip, and connection labor.
7. Low voltage, fire alarm and site work
If data, security, or fire alarm is in your scope, take off devices by count and pathway (conduit, sleeves, J-hooks) by length. On the site plan, count pole lights and bases and measure underground conduit — and don’t forget trenching, backfill, and any concrete encasement if it’s yours.
8. Apply labor units
Electrical labor is estimated per item, not per square foot. Each device, fixture, foot of conduit and foot of wire gets a labor unit (hours per each or per 100 feet). Most contractors start from the NECA Manual of Labor Units or a similar published standard and adjust with their own job-cost history.
- Apply difficulty factors for height, access, occupied buildings, or hard ceilings.
- Multiply total hours by your loaded labor rate (wage + burden).
- Add supervision, mobilization, permits, and equipment rental (lifts!) as separate lines.
Then apply overhead and profit — see how to calculate markup for construction bids.
Worked example: 4,000 SF office buildout
Here’s a simplified takeoff for a one-floor office tenant improvement. Labor units below are illustrative only — use NECA units or your own history for real bids.
| Item | Qty | Unit | Example labor unit | Hours |
|---|---|---|---|---|
| Duplex receptacles (assembly) | 60 | EA | 0.50 hr/EA | 30.0 |
| GFCI receptacles (assembly) | 12 | EA | 0.60 hr/EA | 7.2 |
| Switches & sensors (assembly) | 30 | EA | 0.50 hr/EA | 15.0 |
| Type A 2×4 LED troffer + whip | 80 | EA | 0.90 hr/EA | 72.0 |
| Type B downlight | 12 | EA | 0.75 hr/EA | 9.0 |
| Exit / emergency units | 8 | EA | 0.75 hr/EA | 6.0 |
| 3/4″ EMT branch conduit | 1,800 | LF | 4.0 hr/100 LF | 72.0 |
| #12 THHN (1,800 × 3 × 1.10) | 5,940 | LF | 0.6 hr/100 LF | 35.6 |
| 42-circuit panelboard | 1 | EA | 8.0 hr/EA | 8.0 |
| Mechanical connections (RTU, EF) | 4 | EA | 3.0 hr/EA | 12.0 |
| Total | 266.8 hrs |
Note the wire line: 1,800 LF of conduit × 3 conductors × 1.10 makeup = 5,940 LF of #12. That’s the kind of derived quantity you never want to tally by hand. At an example loaded rate of $75/hr, labor is about $20,000 before materials, gear quotes, overhead and profit.
Final check: compare your circuit count against the panel schedule. If the panel shows 34 branch circuits and your home-run count shows 27, you’ve missed something.
Common electrical takeoff mistakes
- Forgetting vertical drops. On a 10-foot ceiling, a receptacle at 18″ needs about 8.5 feet of drop — times every device.
- Missing equipment on other trades’ sheets. Mechanical units, water heaters and kitchen gear often aren’t shown on E-sheets.
- Counting fixtures by appearance, not type tag.
- Double-counting across overlapping sheets (enlarged plans, partial plans, and the full floor plan).
- Ignoring the wiring method note. MC cable vs EMT changes material and labor dramatically.
- Skipping addenda. Read every addendum before you finalize counts.
More on avoiding these in 10 common estimating mistakes subcontractors make.
Doing it faster with software
Doing an electrical takeoff by hand on paper plans is slow and error-prone. Takeoff software lets you click symbols to count them, trace conduit on a scaled PDF, and — in the better tools — turn those counts directly into material, wire, and labor. Here’s what to look for:
- Count tool with types and colors so every device is marked and nothing is counted twice.
- Linear tool with drops — the ability to add vertical lengths per point, not just plan length.
- Assemblies — one click on a receptacle adds the box, ring, device, plate and labor.
- Conduit-to-wire calculation using conductor count and makeup.
- Labor units with difficulty factors, and output to a proposal or Schedule of Values.
Your options fall into a few groups:
- ScopeTakeoff electrical takeoff software — browser-based takeoff with a Division 26 assembly library: devices and fixtures by count, conduit by size and length, wire calculated from the run, NECA-style labor hours, and SOV export. $100/person/month with a 14-day trial.
- Dedicated electrical estimating systems (such as Trimble Accubid, McCormick, and ConEst) — deep electrical databases built for larger electrical contractors, typically sold by quote.
- Automated symbol counting tools such as Countfire, which focus on detecting and counting electrical symbols.
- General takeoff tools (PlanSwift, STACK, Bluebeam) — good for counting and measuring, but you’ll build the electrical pricing yourself.
For a full side-by-side of tools and pricing, see our roundup of the best electrical estimating software.
Frequently asked questions
Count once. Get conduit, wire and labor automatically.